    <p>Hi Stephan,</p>
    <p>Here is an amendment to the status from the DSG;</p>
    <ul>
      <li>George is preparing a P&I and a list of components to
        provide for Dave Kashy for a system using premixed gas. Once the
        components arrive (just a few days from Matheson), the DSG will
        work with the design authority to assemble the gas supply system
        in the EEL.</li>
    </ul>
    <ul>
      <li>Authorization to procure the gas was just granted today.
        Typical time frame for deliver is 6 to 8 weeks, however it is
        possible for an earlier delivery (maybe 4 weeks).</li>
    </ul>
    <p><br>
    </p>
    <p>Regards,</p>
    <p>Marc<br>
    </p>
    <br>
    <div class="moz-cite-prefix">On 4/4/2017 12:05 PM, Marc McMullen
      wrote:<br>
    </div>
    <blockquote cite="mid:c9392815-0e5e-f051-a9b9-9723df32649a@jlab.org"
      type="cite">
      <meta content="text/html; charset=windows-1252"
        http-equiv="Content-Type">
      <p>Hi Stephan,</p>
      <p>Can you please give a status update on the Pressure Systems
        program activities for the MVT and FT, from the detector owners
        point of view. <br>
      </p>
      <p>As for DSG involvement;</p>
      <ul>
        <li> George Jacobs has already forwarded the gas supply P&I
          diagrams and a list of components to Dave Kashy. (3/22/17)<br>
        </li>
        <li> I sent a start up list necessary components for the gas
          controls/monitoring system last week. (3/23/17)<br>
        </li>
      </ul>
      <p><br>
      </p>
      <p>Additionally, will the MVT detectors need to be tested in any
        location, other than the EEL 124 clean room (For instance: EEL
        125 which is the room right beside the clean room)?</p>
      <p>Finally, the DSG will need authorization to hook up any gas to
        these detectors from the system owner (Bob Miller) or the design
        authority (Dave Kashy), and authorization may take many weeks.
        Dave Kashy may be able to comment on the time table of pressure
        systems calculations, examinations, and tests.<br>
      </p>
      <p>Regards,</p>
      <p>Marc<br>
      </p>
      <br>
      <div class="moz-cite-prefix">On 3/14/2017 10:46 AM, Marc McMullen
        wrote:<br>
      </div>
      <blockquote
        cite="mid:90b6dcab-6aa1-eb13-88bc-424f579ee7b7@jlab.org"
        type="cite">Hi Stephan, <br>
        <br>
        <br>
        As mentioned in this morning teleconference, both the detectors
        have complete signatures on their respective Operational Safety
        Procedure documents for use in the EEL building. The EEL
        documents do not cover operation in Hall B. <br>
        <br>
        In addition to the OSP, JLab requires a pressure systems
        analysis to be conducted for all gas systems. The initial step
        is the naming of  a system owner (Bob Miller) and a design
        authority (DA). Bob named Dave Kashy as the DA for the MVT and
        FVT. <br>
        <br>
        In preparation for the SVT/MVT integration and testing slated
        for this summer, as well as the installation of the FT in the
        hall (You mentioned July), it is important to begin the pressure
        systems analysis as soon as possible. Dave Kashy will need
        documentation for the MVT and FVT distribution systems in order
        to start the process. Per Bobs request in the meeting, please
        contact him directly. Aditionally, please add <a
          moz-do-not-send="true" class="moz-txt-link-abbreviated"
          href="mailto:dsg-mvt@jlab.org">dsg-mvt@jlab.org</a> as well as
        <a moz-do-not-send="true" class="moz-txt-link-abbreviated"
          href="mailto:dsg-ft@jlab.org">dsg-ft@jlab.org</a> (for FT
        details) to those communications so that the DSG can be informed
        of the status. As the DA, Dave will inform us when we can flow
        gas for each respective detector. <br>
        <br>
        Regards, <br>
        <br>
        <br>
      </blockquote>
      <br>
      <pre class="moz-signature" cols="72">-- 
Marc McMullen
Detector Support Group
757-269-7738</pre>
      <br>
      <fieldset class="mimeAttachmentHeader"></fieldset>
      <br>
      <pre wrap="">_______________________________________________
Dsg-ft mailing list
<a class="moz-txt-link-abbreviated" href="mailto:Dsg-ft@jlab.org">Dsg-ft@jlab.org</a>
<a class="moz-txt-link-freetext" href="https://mailman.jlab.org/mailman/listinfo/dsg-ft">https://mailman.jlab.org/mailman/listinfo/dsg-ft</a>
</pre>
    </blockquote>
    <br>
    <pre class="moz-signature" cols="72">-- 
Marc McMullen
Detector Support Group
757-269-7738</pre>