[Dsg-hallbgas] Forward from Amrit
Youri Sharabian
youris at jlab.org
Wed Jul 12 13:00:36 EDT 2017
Hi Marc,
Regarding the HTCC: - We are waiting for DA approval of the HTCC volume purging procedure, related procurement and such that would allow us to start replacing components inside the volume. - We been informed by Hall B Engineering group and then during Hall B meeting as well that the DA will take care about HTCC later this month after they are done with Hall B target.Please let me know if more details needed.Thank you. Regards, Youri
----- Original Message -----
From: Marc McMullen <mcmullen at jlab.org>
To: dsg-hallbgas at jlab.org
Sent: Wed, 12 Jul 2017 11:26:07 -0400 (EDT)
Subject: [Dsg-hallbgas] Forward from Amrit
Subject:
Fwd: hallb gas system status.
From:
Amrit Yegneswaran <yeg at jlab.org>Date:
7/12/2017 10:58 AMTo:
Dsg-hallbgas <dsg-hallbgas-bounces at jlab.org>
george,
please update the status sheet(attached) for today's meeting.
amrit
From: "Amrit Yegneswaran"
<yeg at jlab.org>
To: "Burkert Volker" <burkert at jlab.org>,
"Dsg-hallbgas" <dsg-hallbgas-bounces at jlab.org>
Cc: "Patrizia Rossi" <rossi at jlab.org>
Sent: Tuesday, June 27, 2017 9:51:29 AM
Subject: hallb gas system status.
attached find Hall B gas system's current status, provided by
george jacobs.
system owners! provide ASAP estimated date of pressure
system approval for your system, if it is pending DA's
approval or if the status is unknown.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_gas/attachments/20170712/0a9cc14e/attachment-0002.html>
More information about the Dsg-hallbgas
mailing list