Hi Tanya,

I am ordering mass flow controllers for the Hall B ALERT gas system. These have a 3 week lead time on them. Are you able to add the CPO signature for this req?

PR428219<https://misportal.jlab.org/reqs/prs/428219#ShowGeneralTab>

Regards,
Marc McMullen