Hi,

I was in the hall this morning and will take the opportunity to request 
that the temporary extension cord that runs between space frame deck1 
south to space frame deck3 south be removed during the upcoming down time.

The equipment in rack L3-15 [space frame deck 3 south] is powered from a 
single phase UPS at the bottom of the rack. This UPS can be plugged into 
the utility outlet that is a few feet from the rear of the L3-15 rack.

Thanks,

-Chris

~~~~~~~~~~~~~~~~~~

On 12/10/2018 9:30 AM, mcmullen at jlab.org wrote:
>
>
>   Hall B Gas System Alarms <https://logbooks.jlab.org/entry/3636990>
>
>   * Edit
>     <https://logbooks.jlab.org/entry/3636990/edit?destination=email/send>
>   * Delete
>     <https://logbooks.jlab.org/entry/3636990/delete?destination=email/send>
>
> Lognumber 3636990 <https://logbooks.jlab.org/entry/3636990>. Submitted 
> by mcmullen <https://logbooks.jlab.org/user/mcmullen> on Mon, 
> 12/10/2018 - 09:28 
> <https://logbooks.jlab.org/entries?start_date=1544448483&end_date=1544455683&book=HBLOG>. 
>
>
> Logbooks: 	HBLOG <https://logbooks.jlab.org/book/hblog>
> Entry Makers: 	mcmullen
>
> Hall B Gas Alarms for the LTCC Gas and DC Gas will be temporarily 
> disabled due to testing and integration of LTCC signals. This entry 
> will be updated when the alarms are re-enabled.
>
>
> _______________________________________________
> Dsg-dc mailing list
> Dsg-dc at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-dc
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_ltcc/attachments/20181210/3d699c7a/attachment-0002.html>


More information about the Dsg-ltcc mailing list