Hi,

The forward carriage gas interface chassis has been reinstalled. The software is operating normally. DSG will start connecting the S6 supply and return solenoids later this week. The S2 solenoids have already been connected and tested with the software for functionality.

Hall B is in the process of installing the additional pressure sensors and routing the cables to the panel on FC deck 1. DSG will then connect the sensors to the system and begin testing the upgrade.



Marc

________________________________
From: dsg-hallb_ltcc <dsg-hallb_ltcc-bounces at jlab.org> on behalf of Marc Mcmullen <mcmullen at jlab.org>
Sent: Tuesday, May 17, 2022 10:45 AM
To: dsg-hallb_ltcc at jlab.org <dsg-hallb_ltcc at jlab.org>
Cc: Bob Miller <rmiller at jlab.org>; Morgan Cook IV <mcookiv at jlab.org>
Subject: [dsg-hallb_ltcc] LTCC upgrade

Hi,

I am going to start work on the Hall B gas system Forward Carriage chassis. The power to the controls system sensors will be interrupted. This will not affect the safety elements, as those components are passive.

Regards,
Marc
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_ltcc/attachments/20220517/8c249d04/attachment.html>


More information about the dsg-hallb_ltcc mailing list