[Dsg-hallb_magnets] Solenoid PLC Programming
Pablo Campero
campero at jlab.org
Mon Nov 21 09:52:41 EST 2016
Hello Ruben,
The PLC program to test the Voltage Tap is ready and also the links to the EPICs screen were defined. So I think that we can make the test today.
I'm currently working in the Solenoid Cryogenics using the PID spreadsheet that was updated last week, and also I'm working in the Solenoid vacuum system.
I'm waiting the information for the solenoid voltage tap comparators (calculations), limits for trip interlocks magnet, to complete the Magnet Calculation and Magnet Interlocks program, I need temperature tables to implement in the Cryocons . We can discuss the details tomorrow in the meeting.
With Regards
Pablo Campero
From: "Ruben Fair" <rfair at jlab.org>
To: "Pablo Campero Rojas" <campero at jlab.org>
Cc: "Renuka Rajput-Ghoshal" <renuka at jlab.org>
Sent: Sunday, November 20, 2016 8:40:03 AM
Subject: Solenoid PLC Programming
Hi Pablo,
I understand that you are part of the voltage injection tests tomorrow morning in the hall. Does this mean that the VT PLC sub-program is now ready? And what about the links to the relevant EPICS screens - have you been liaising with Wesley to ensure the EPICS screen reflects what we want?
Can you please give me an update on all the PLC programming required for the Solenoid?
Can I also ask, what other projects or work are you involved in at present and will that work prevent you from completing all the PLC programming by end Nov 2016 (except the final debugging and testing of course which can only happen during commissioning)
What additional information are you waiting for from us to enable you to complete the programming in time?
If you could respond by tomorrow morning sometime that would be great. We have a Director's meeting in the afternoon where we are expected to report on the progress made so far.
Regards
Ruben
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20161121/8e6e2418/attachment.html>
More information about the Dsg-hallb_magnets
mailing list