[Dsg-hallb_magnets] SST- Instrumentation Test plan PLC-EPICS

Renuka Rajput-Ghoshal renuka at jlab.org
Tue Feb 21 08:28:44 EST 2017


Thanks Pablo,
I will look at this list in detail today and we can discuss this tomorrow after our meeting.
Scot and I have already checked most of these drawings and connections. 
We need to check the PLC and EPICS.

Thanks
Renuka

----- Original Message -----
From: "Pablo Campero" <campero at jlab.org>
To: "dsg-hallb magnets" <dsg-hallb_magnets at jlab.org>
Sent: Monday, February 20, 2017 5:08:57 PM
Subject: [Dsg-hallb_magnets] SST- Instrumentation Test plan PLC-EPICS

Hello Renuka, 

Attached find proposed plan to test the Instrumentation int the Solenoid Service tower and Vacuum system. 

Please fill out and confirm sensors / instrumentation that are already installed and tested in the columns C and D of this spreadsheet. 

Any comments and questions just let me know. 


Thanks, 
Pablo 

_______________________________________________
Dsg-hallb_magnets mailing list
Dsg-hallb_magnets at jlab.org
https://mailman.jlab.org/mailman/listinfo/dsg-hallb_magnets