[Dsg-hallb_magnets] Unable to perform Torus pre-power-up interlock checklist today

Ruben Fair rfair at jlab.org
Fri Jan 20 16:11:21 EST 2017


Ok - thank you Tyler. 

Regards 

Ruben 



From: "Tyler Lemon" <tlemon at jlab.org> 
To: "dsg-hallb magnets" <dsg-hallb_magnets at jlab.org> 
Sent: Friday, January 20, 2017 4:04:36 PM 
Subject: [Dsg-hallb_magnets] Unable to perform Torus pre-power-up interlock checklist today 

Hello Ruben and Probir, 

This afternoon at 2:00PM, Pablo, Amanda, and I went to Hall B to start on the Torus Pre-power-up interlock checklist. We were not able to perform any of the 18 tasks on the checklist because the MPS was not able to be powered on. 

We will try again to start the checklist on Monday after the MPS is able to be powered on. 

Best regards, 
Tyler 

_______________________________________________ 
Dsg-hallb_magnets mailing list 
Dsg-hallb_magnets at jlab.org 
https://mailman.jlab.org/mailman/listinfo/dsg-hallb_magnets 
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20170120/b0c0c29a/attachment.html>


More information about the Dsg-hallb_magnets mailing list