[Dsg-hallb_magnets] Torus Pre-power-up interlock checklist P027 Complete
Ruben Fair
rfair at jlab.org
Tue Jan 24 18:31:07 EST 2017
Thank you guys
Ruben
> On Jan 24, 2017, at 3:38 PM, Tyler Lemon <tlemon at jlab.org> wrote:
>
> Hello,
>
> Pablo and I completed all (17 of 17) tasks required for the KPP Torus Pre-power-up Interlock Checklist P027.
>
> Attached is a scanned copy of the completed P027. Note: not all checks performed, as they were only necessary for full current commissioning (occurred in October 2016).
>
> During some of the tests, the Controlled Ramp Down Cryo interlock tripped due to low VCL flow and Nitrogen Overpressure. We commented these interlocks out of the PLC so we could complete the checklist. This is noted on page 20 of the checklist.
>
> We will take the hard copy to Hall B and place it in the binder near the controls racks on Space Frame Level 2.
>
> Best regards,
> Tyler
>
> <P027 Hall B Pre-power-up Interlock Checkout Procedure 2017-01-24.pdf>