[Dsg-hallb_magnets] Hall B Solenoid - Power Up ERR - Close Out Actions
Ruben Fair
rfair at jlab.org
Fri Jul 14 17:24:15 EDT 2017
Ok never mind
> On Jul 14, 2017, at 4:56 PM, Pablo Campero <campero at jlab.org> wrote:
>
> Hi Brian,
>
> The E-WEB was installed and configured, but I still need to configure the EWEB module in the Solenoid PLC project program.
> To implement the module properly I need to go off-line with the Solenoid PLC controller, since today and during the weekend the EV valves need to be operated I will implement this configurations next week in order to complete all the Time Sync between the Solenoid PLC and the NTP Jalb time.
>
> Best Regards,
> Pablo
>
> From: "Brian Eng" <beng at jlab.org>
> To: "Ruben Fair" <rfair at jlab.org>
> Cc: "Wesley Moore" <wmoore at jlab.org>, "Probir Ghoshal" <ghoshal at jlab.org>, "Renuka Rajput-Ghoshal" <renuka at jlab.org>, "Pablo Campero Rojas" <campero at jlab.org>, "George Biallas" <biallas at jlab.org>, "Nick Sandoval" <sandoval at jlab.org>, "John Hogan" <hogan at jlab.org>, "Glenn Young" <gyoung at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "Dave Kashy" <kashy at jlab.org>, "Joseph Matalevich" <josephm at jlab.org>, "rossi patrizia" <rossi at jlab.org>, "Eugene Pasyuk" <pasyuk at jlab.org>, "Tyler Lemon" <tlemon at jlab.org>, "Scot Spiegel" <spiegel at jlab.org>
> Sent: Friday, July 14, 2017 1:52:32 PM
> Subject: Re: Hall B Solenoid - Power Up ERR - Close Out Actions
>
> https://logbooks.jlab.org/entry/3478890 - addresses the cRIOs
>
> Scot and Pablo already setup the EWEB module for the Solenoid PLC.
>
> You can consider that comment complete, all controllers are synchronized with the Jlab NTP server.
>
> > On Jul 14, 2017, at 1:29 PM, Ruben Fair <rfair at jlab.org> wrote:
> >
> > Thank you kindly
> >
> >
> > From: "Brian Eng" <beng at jlab.org>
> > To: "Ruben Fair" <rfair at jlab.org>
> > Cc: "wmoore" <wmoore at jlab.org>, "Probir Ghoshal" <ghoshal at jlab.org>, "Renuka Rajput-Ghoshal" <renuka at jlab.org>, "Pablo Campero Rojas" <campero at jlab.org>, "George Biallas" <biallas at jlab.org>, "Nick Sandoval" <sandoval at jlab.org>, "John Hogan" <hogan at jlab.org>, "Glenn Young" <gyoung at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "David Kashy" <kashy at jlab.org>, "Joseph Matalevich" <josephm at jlab.org>, "rossi patrizia" <rossi at jlab.org>, "Eugene Pasyuk" <pasyuk at jlab.org>, "Tyler Lemon" <tlemon at jlab.org>, "Scot Spiegel" <spiegel at jlab.org>
> > Sent: Friday, July 14, 2017 1:20:02 PM
> > Subject: Re: Hall B Solenoid - Power Up ERR - Close Out Actions
> >
> > Since 3 out of the 4 cRIOs run Linux they all have ntpd installed which will keep the time in sync with the JLab NTP server. I've verified that they all have it installed and it is running (has an updated drift file).
> >
> > The odd one out is the solenoid LV cRIO which runs VxWorks, it can sync to SNTP servers according to documentation, so I'm in the process of setting that up.
> >
> > I'll send another email once all the cRIOs have been verified to have properly synchronized clocks.
> _______________________________________________
> Dsg-hallb_magnets mailing list
> Dsg-hallb_magnets at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-hallb_magnets
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20170714/4d2908be/attachment.html>
More information about the Dsg-hallb_magnets
mailing list