[Dsg-hallb_magnets] Solenoid PLC Off- Line
Pablo Campero
campero at jlab.org
Tue Jul 25 14:33:31 EDT 2017
Hello Ruben,
I think that this afternoon there is no activity related with the test of the instrumentation. Can you confirm that? I was planning to go off line with the PLC to complete the configurations of the EWEB module to the time synchronization in the Solenoid PLC.
Please let me know if I can go ahead.
Regards,
Pablo
From: "Pablo Campero" <campero at jlab.org>
To: "Ruben Fair" <rfair at jlab.org>
Cc: "dsg-hallb magnets" <dsg-hallb_magnets at jlab.org>
Sent: Tuesday, July 18, 2017 9:12:43 AM
Subject: Solenoid PLC Off- Line
Hello Ruben,
Are there any operations running at this time with the EV valves in the SST, or other related instrumentation control that you require right now?. I was planning to complete with the configurations required to the time synchronization in the Solenoid PLC program, and I need to go off-line with it to apply the changes.
Please let me know if I can go ahead; this will not take more than 15 min if everything runs as expected.
Best Regards,
Pablo
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20170725/4d9b0b06/attachment.html>
More information about the Dsg-hallb_magnets