Dear team,
Could we meet at the Counting house Hall B at 900 hrs.
The plan is to run the magnet down to 100 A and dump a couple of time to see the timings with -j-s-d.
Following that i will need to sweep the magnet area before charging the magnet to full field.
Next will charge the magnet to full field and park till Tuesday afternoon (i will talk to Eugene P) to see who is on call else will run the magnet down .
Regards
Probir
    
    