[Dsg-hallb_magnets] High and Low pass/fail values for Torus pre-powerup instrumentation checks?

Tyler Lemon tlemon at jlab.org
Thu Jun 3 12:27:50 EDT 2021


Hello,

We're currently performing Hall B Magnet pre-power up checks.

Part of this is the instrumentation check list.

For the Solenoid, Brian wrote a nice program that automates the check and posts results to the Solenoid logbook. Since there isn't an equivalent program for the Torus, I'm in the process of making one.

For the Torus, what are the limits sensors should be within for it to pass the checks?

Could someone fill out the attached spreadsheet with the limits?

If a resource for the check limits already exists, can someone send it to me?

-Tyler
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20210603/fac6840f/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Torus instrumemtation check PVs.xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 16342 bytes
Desc: Torus instrumemtation check PVs.xlsx
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20210603/fac6840f/attachment-0001.xlsx>


More information about the Dsg-hallb_magnets mailing list