Hi Probir,
I don't know how long the installation and configuration of the new network switch would take since computer center handles those parts.
If everything goes smoothly, our part (moving the network connection, making new network cables if needed, and testing) could be done in one day.
Since the PLCs rely on network connection for communicating to several remote devices for cryogenic monitoring, it would be best if we allotted additional time after the swap in the event that cryogenics are significantly affected by the temporary loss of network.
-Tyler
________________________________
From: Probir Ghoshal <ghoshal at jlab.org>
Sent: Wednesday, September 1, 2021 10:23 AM
To: Tyler Lemon <tlemon at jlab.org>; dsg-hallb magnets <dsg-hallb_magnets at jlab.org>
Cc: Nick Sandoval <sandoval at jlab.org>; Marco Battaglieri <battagli at jlab.org>; Denny Insley <dinsley at jlab.org>
Subject: Re: FROM FEB 2020 - Additional network switch in the rack row with Rack L2 in Hall B
Tyler,
Thanks for the update on the N/w switch.
I agree, we must get one as my recommendation for the additional network switch, as discussed and agreed in the past.
Please gain remind the team, how long will this take to put/add and test before we say all done and completed in the system.
Known with the timeline, will request Marco and Denny I/Bob M if any down time will be available before Dec2021.
Regards
Probir
________________________________
From: Dsg-hallb_magnets <dsg-hallb_magnets-bounces at jlab.org> on behalf of Tyler Lemon <tlemon at jlab.org>
Sent: Wednesday, September 1, 2021 9:58 AM
To: dsg-hallb magnets <dsg-hallb_magnets at jlab.org>
Subject: [Dsg-hallb_magnets] FROM FEB 2020 - Additional network switch in the rack row with Rack L2 in Hall B
Hello,
Back in February 2020, we had an issue with the Solenoid and Distribution Box controls' networking that prompted us to look into getting an additional network switch put in the racks so the Solenoid and DBX controls would be on separate network switches, but at the time, I guess computer center didn't have any switches on hand. The computer center request and correspondence is below.
Is this something that we would still want?
I'm guessing that we would want to wait until the next extended down period before changing any controls setup, but we could get computer center to reserve a network switch since it took 1.5+ years for them to finally get one.
-Tyler
________________________________
From: IT Service Desk <jlab at servicenowservices.com>
Sent: Wednesday, September 1, 2021 9:49 AM
To: Tyler Lemon <tlemon at jlab.org>
Subject: Your Incident INC0023233 has comments added - In Hall B on Space Frame Level 2, we need an additional network switch in the rack row with Rack L2
Subject: In Hall B on Space Frame Level 2, we need an additional network switch in the rack row with Rack L2
Incident: INC0023233
Comments:
________________________________
09-01-2021 09:49:44 AM EDT - Andrew Seitz Additional comments
Do you still need this switch? The stock has finally arrived and we can install one if you need it.
________________________________
03-03-2020 01:29:47 PM EST - Andrew Seitz Additional comments
Gotcha, I'll see about getting a new switch.
________________________________
03-03-2020 01:19:50 PM EST - Tyler Lemon Additional comments
reply from: tlemon at jlab.org
Hi Andrew,
Sorry for the long delay in my reply.
We'd like an additional switch in that area since there are two controls systems (Hall B Solenoid and Hall B Distribution Box) that are connected to network in that switch. The goal would be to have the Solenoid and Distribution Box on different network switches to prevent an issue with one switch from taking out two systems.
It's okay if it takes a while for the switch to be installed. I wanted to get the incident report in in case it did just take a while to get the switch in. It's also fine if the installation doesn't take place until after the on-going run is completed.
Thanks,
Tyler
________________________________
From: IT Service Desk <jlab at midatl.service-now.com>
Sent: Thursday, February 20, 2020 9:51 AM
To: Tyler Lemon <tlemon at jlab.org>
Subject: Your Incident INC0023233 has comments added - In Hall B on Space Frame Level 2, we need an additional network switch in the rack row with Rack L2
Subject: In Hall B on Space Frame Level 2, we need an additional network switch in the rack row with Rack L2
Incident: INC0023233
Comments:
________________________________
02-20-2020 09:50:46 AM EST - Andrew Seitz Additional comments
Sorry, I didn't see this ticket until today...
Is that bethsw8? Yesterday we replaced that switch so all of the ports should now be good. I count 6 free auto-vlan ports, is that enough? We don't really have a good switch to give you right now, we'd have to get one.
________________________________
02-17-2020 02:07:14 PM EST - Tyler Lemon Additional comments
In Hall B on Space Frame Level 2, we need an additional network switch in the rack row with Rack L2-10. The switch currently in that rack is full and we would like to have spare ports to use in the event of a port failure.
Considering the halls are running experiments, it is understandable if the switch cannot be installed until the summer shut down.
You can view all the details of the incident by following the link below:
Take me to the Incident<https://jlab.service-now.com/nav_to.do?uri=incident.do?sys_id=104a6d91db4780100545341f7c9619de>
Original Request:
In Hall B on Space Frame Level 2, we need an additional network switch in the rack row with Rack L2-10. The switch currently in that rack is full and we would like to have spare ports to use in the event of a port failure.
Considering the halls are running experiments, it is understandable if the switch cannot be installed until the summer shut down.
Ref:MSG0131756_o0v153yNyY740pN4DFxm
________________________________
02-20-2020 09:50:46 AM EST - Andrew Seitz Additional comments
Sorry, I didn't see this ticket until today...
Is that bethsw8? Yesterday we replaced that switch so all of the ports should now be good. I count 6 free auto-vlan ports, is that enough? We don't really have a good switch to give you right now, we'd have to get one.
________________________________
02-17-2020 02:07:14 PM EST - Tyler Lemon Additional comments
In Hall B on Space Frame Level 2, we need an additional network switch in the rack row with Rack L2-10. The switch currently in that rack is full and we would like to have spare ports to use in the event of a port failure.
Considering the halls are running experiments, it is understandable if the switch cannot be installed until the summer shut down.
You can view all the details of the incident by following the link below:
Take me to the Incident<https://urldefense.proofpoint.com/v2/url?u=https-3A__jlab.servicenowservices.com_nav-5Fto.do-3Furi-3Dincident.do-3Fsys-5Fid-3D104a6d91db4780100545341f7c9619de&d=DwMFaQ&c=CJqEzB1piLOyyvZjb8YUQw&r=xJvfz8d-IPB1CokOM-U5MA&m=ykGlOxM_oMnpfJQESZNQ2j4l6eWYN2ZUkFs1C84aEl0&s=WkmnsPo0ayE56jq9Jns7zl2I1PodIf8Qv6tF67_Sdrc&e=>
Original Request:
In Hall B on Space Frame Level 2, we need an additional network switch in the rack row with Rack L2-10. The switch currently in that rack is full and we would like to have spare ports to use in the event of a port failure.
Considering the halls are running experiments, it is understandable if the switch cannot be installed until the summer shut down.
Ref:MSG0402691_jocTKyvjHMtwohDSwlUe
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20210907/38b2001a/attachment-0001.html>
More information about the Dsg-hallb_magnets
mailing list