[Dsg-hallb_prad_ii] PRad-II status updates

Pablo Campero Rojas campero at jlab.org
Mon Mar 16 12:13:43 EDT 2026


Hello All,

Please find the status update for the PRad project below:

- Turbo Pump Testing: Tested five turbo pump readouts at zero Hz in LabVIEW. Upstream turbopumps are awaiting installation and testing.
- Leak Test Preparation: Verified local control of five turbo pumps via DCU units. Priority control settings were adjusted to bypass interlocks in preparation for the leak test scheduled to begin today.
- Next Steps: Once leak checks and the installation/alignment of the target cell are complete, DSG will proceed with the remaining instrumentation connections and communication tests.
- Pressure Sensors: Working on a new request to read three pressure sensors (upstream, chamber, and downstream) on LabVIEW program. One cable extension for downstream pressure sensor has been completed by Mindy.
- EPICS: Started testing the main PRad-II EPICS screen.


Regards,
Pablo

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_prad_ii/attachments/20260316/ae126898/attachment.htm>


More information about the Dsg-hallb_prad_ii mailing list