    Hi Walt,<br>
    <br>
    All the components for this are currently in EEL rm 125. <br>
    <br>
    This diagram was part of the RICH status update from ~ 3 weeks ago.<br>
    <br>
    <img alt="" src="cid:part1.64F956C2.73C741FB@jlab.org" height="709"
      width="918"><br>
    <br>
    <div class="moz-cite-prefix">On 10/18/2016 11:11 AM, Walt Akers /
      JLAB wrote:<br>
    </div>
    <blockquote cite="mid:58063BAD.9020306@jlab.org" type="cite">George:
      <br>
      <br>
      We have a plan for the layout of the room, but I had not received
      any information
      <br>
      about the addition of electrical infrastructure.  We'll need to do
      the following:
      <br>
      <br>
      a) walk through the plan and determine where the power needs to be
      installed to
      <br>
      support the compressor,
      <br>
      b) determine if there is any power in the area that is available
      to support this load,
      <br>
      if not we'll have to determine where we're routing it from,
      <br>
      c) come up with a price and schedule to do the work in time to
      support this activity.
      <br>
      <br>
      If the price is too high, we may need to think about alternatives,
      including using
      <br>
      a different compressor OR relocating the work to where the power
      is available.
      <br>
      <br>
      Still, if there is a welding outlet in the room (I'm not sure), we
      may be able to
      <br>
      purchase and use one of the new Bertha's to support this activity.
      That would
      <br>
      be less than $10,000.
      <br>
      <br>
      I will walk the area with Jason as soon as possible. In the
      meantime, though,
      <br>
      please send me a list of all of the electrical and mechanical
      infrastructure that
      <br>
      you need to have installed in the room so we can consider it in
      its entirety.
      <br>
      <br>
      Jason:  I'm doing a walk through of EEL 126 today (2:00 pm) with
      someone else
      <br>
      from Facilities, do you want to check this out at the same time?
      <br>
      <br>
      Walt
      <br>
      <br>
      George Jacobs wrote:
      <br>
      <blockquote type="cite">Hi Walt,
        <br>
        <br>
        The RICH air compressor has arrived, it is currently in EEL rm
        125. The plan is to install it in the rm 124 clean room. This is
        a large unit and requires a new power feed, 208v 3 phase 70 amp
        service. I have place a work order to run this new power feed.
        FM&L needs an updated floor plan and charge codes for this.
        The air cooling valve panel and tank are also complete, rm 125.
        I thought these were already in the floor plan.
        <br>
        <br>
        Thanks,
        <br>
        George
        <br>
        <br>
        On 10/18/2016 10:43 AM, Jason Willoughby wrote:
        <br>
        <blockquote type="cite">George,
          <br>
          <br>
          Has this compressor been coordinated through Walt?  This
          compressor is the first time I've seen such a thing and this
          was not on Walt's overall plan for the room.  Please
          coordinate with him and get back to me with a charge code for
          the work.  There really isn't a viable close 208 70A source in
          the area, which means the costs of this installation are going
          to be a bit high.
          <br>
          <br>
          Jason Willoughby
          <br>
          FM&L Electrical Engineer
          <br>
          Thomas Jefferson National Accelerator Facility
          <br>
          628 Hofstadter Road STE 1
          <br>
          Newport News, VA 23606
          <br>
          (757)-269-5372
          <br>
        </blockquote>
        <br>
        -- <br>
        George Jacobs
        <br>
        Jefferson Lab (TJNAF)
        <br>
        STE 12
        <br>
        12000 Jefferson Ave.
        <br>
        Newport News, VA 23606
        <br>
        <br>
        (office) 757-269-7115
        <br>
        <br>
        (cell)   757-876-0480
        <br>
        <br>
        (<a class="moz-txt-link-abbreviated" href="mailto:email)jacobsg@jlab.org">email)jacobsg@jlab.org</a>
        <br>
        <br>
        (website)<a class="moz-txt-link-freetext" href="https://userweb.jlab.org/~jacobsg">https://userweb.jlab.org/~jacobsg</a>
        <br>
      </blockquote>
      <br>
      <br>
    </blockquote>
    <br>
    <pre class="moz-signature" cols="72">-- 
George Jacobs
Jefferson Lab (TJNAF)
STE 12
12000 Jefferson Ave.
Newport News, VA 23606

(office) 757-269-7115

(cell)   757-876-0480

(email) <a class="moz-txt-link-abbreviated" href="mailto:jacobsg@jlab.org">jacobsg@jlab.org</a>

(website) <a class="moz-txt-link-freetext" href="https://userweb.jlab.org/~jacobsg">https://userweb.jlab.org/~jacobsg</a></pre>
  </body>
</html>