    <p>Hi Marco,</p>
    <p>We are still waiting on the approval of the RICH detector shell
      assembly TOSP, however the WEEK 1 portion of the schedule can be
      done with a written Task Hazard Analasys (we have this completed
      already).</p>
    <p> Additionally, your plan has scaffolding listed in a few areas.
      We had already decided to use man lifts instead, if you think
      scaffolding is absolutely necessary, we should discuss it and
      changes will have to be made to the assembly TOSP.</p>
    <p>Once we have the exact locations of the holes to be drilled,
      machining support  from the mechanical group will be necessary to
      install the anchors in the floor. Bob Miller suggested to contact
      Doug or Denny at the appropriate time in the schedule for this
      portion of the task.<br>
    </p>
    <p>The current TOSP does not cover installation of electronics (or
      mirrors), as an installation procedure was not available at the
      time. <br>
    </p>
    <p>Thanks,</p>
    <p>Marc<br>
    </p>
    <br>
    <div class="moz-cite-prefix">On 1/20/2017 6:40 AM, Marco Mirazita
      wrote:<br>
    </div>
    <blockquote
      cite="mid:6350897993c95acf9f5bb4f23fb5e852@webmail.lnf.infn.it"
      type="cite">Dear all,
      <br>
      now that the RICH has finally arrived at JLab, we have just to
      assembly it!
      <br>
      <br>
      My original work plan was organized in two assembly sessions, the
      first one scheduled right after the delivery and the second one
      later on.
      <br>
      <br>
      However, at least to my knowledge, we are still waiting for the
      final approval of the OSP that will allow us to start the work in
      the EEL124.
      <br>
      In addition, I can suppose that in February the JLab people will
      be fully busy with the preparation and running of the CLAS12 KPP
      data taking.
      <br>
      Thus, I replanned the work in one single, 3-week long, assembly
      session that could take place from March 6 to 24.
      <br>
      I attached a preliminary schedule of the work to be done, with
      indication of the support we will need at every step
      (scaffoldings, forklift, etc.).
      <br>
      Please let me know as soon as possible if you agree with this new
      plan.
      <br>
      If necessary, we could set up phone meetings to better define the
      various phases of the work.
      <br>
      <br>
      Best regards, and than again to all the people that contributed to
      the receiving of the RICH
      <br>
      Marco
      <br>
      <br>
      <fieldset class="mimeAttachmentHeader"></fieldset>
      <br>
      <pre wrap="">_______________________________________________
Dsg-rich mailing list
<a class="moz-txt-link-abbreviated" href="mailto:Dsg-rich@jlab.org">Dsg-rich@jlab.org</a>
<a class="moz-txt-link-freetext" href="https://mailman.jlab.org/mailman/listinfo/dsg-rich">https://mailman.jlab.org/mailman/listinfo/dsg-rich</a>
</pre>
    </blockquote>
    <br>
    <pre class="moz-signature" cols="72">-- 
Marc McMullen
Detector Support Group
757-269-7738</pre>