    I believe operation of this unit will be limited before it is moved
    to  hall B. Perhaps a temporary drain pan is all that is needed?<br>
    <br>
    George<br>
    <br>
    <div class="moz-cite-prefix">On 7/31/2017 10:38 AM, Carroll Jones
      wrote:<br>
    </div>
    <blockquote type="cite"
      cite="mid:8E9934FE-866E-47BA-97C1-F69416681577@jlab.org">
      <pre wrap="">Is this compressor an air compressor or refrigeration compressor?  Drainage from her compresses have all and must be removed before draining into the sanitary drain.

For additional information or clarification, please contact me at 757–8 76–1778.

Sincerely,

Carroll W Jones

Sent from my iPhone

</pre>
      <blockquote type="cite">
        <pre wrap="">On Jul 31, 2017, at 9:17 AM, Walt Akers <a class="moz-txt-link-rfc2396E" href="mailto:akers@jlab.org"><akers@jlab.org></a> wrote:

Tyler:

There are a variety of drains nearby.  The most likely candidate would
be in one of the utility closets on the main hallway.  Notably, this would
probably require the installation of a small pump to deliver the water
from the compressor to the utility room.

I'm CCing Carroll Jones on this, because it would certainly involve
some design support from Facilities to make this happen (unless there
is already a floor drain nearby).

Walt

Tyler Lemon wrote:
</pre>
        <blockquote type="cite">
          <pre wrap="">Hello,

One note left out from my email on Friday: we found during the test of the EEL compressor that there is a drain on each of the compressors where water will shoot out every few minutes.

The drain needs a 5/16-inch diameter line to lead to some sort of reservoir. Brian and I tried to find a 5/16-inch diameter line in the Hall B Gas Shed but could not find one. Do we have anything that could be used for the compressor drain line?

To hold the drain water, a temporary solution could be to use a bucket, but we do not know how much water is produced in a given time so there is a chance the bucket could overflow if not checked regularly.

Walt,
Is there already a drain in EEL 125 that we could run the compressor's drain line to?

Doug,
Is there someplace the compressors could drain to in Hall B?

Best regards,
Tyler

------------------------------------------------------------------------
*From: *"Tyler Lemon" <a class="moz-txt-link-rfc2396E" href="mailto:tlemon@jlab.org"><tlemon@jlab.org></a>
*To: *"dsg-rich" <a class="moz-txt-link-rfc2396E" href="mailto:dsg-rich@jlab.org"><dsg-rich@jlab.org></a>, "DeAnn Maddox" <a class="moz-txt-link-rfc2396E" href="mailto:maddox@jlab.org"><maddox@jlab.org></a>, "Walt Akers" <a class="moz-txt-link-rfc2396E" href="mailto:akers@jlab.org"><akers@jlab.org></a>, "Joshua Johnson" <a class="moz-txt-link-rfc2396E" href="mailto:joshua.johnson@us.atlascopco.com"><joshua.johnson@us.atlascopco.com></a>, "paul stanko" <a class="moz-txt-link-rfc2396E" href="mailto:paul.stanko@us.atlascopco.com"><paul.stanko@us.atlascopco.com></a>
*Sent: *Friday, July 28, 2017 4:56:41 PM
*Subject: *[Dsg-rich] RICH compressors successfully powered

Hello,

This afternoon we successfully powered on both RICH compressors in the EEL and Hall B.

For the compressor in the EEL, we turned it on and set a maximum output pressure of 70 psi on the compressor. We then let the compressor run until it turned itself off when reaching an output pressure of 70 psi. After this, we stopped the compressor and vented the attached gas tank. We also got the MAC address for this compressor and Brian has contacted Sergey to get an IP address assigned to the compressor. The compressor's emergency stop button has been pressed, preventing the compressor output from being enabled.

For the compressor in Hall B, we only turned it on and made sure that it is able to run correctly. We left this compressor powered on, but not running.

Thank you to DeAnn for making sure all visitors were properly registered to be able to get on site. Thank you to Walt for quickly arranging the short-notice electrical work that needed to be done today. Also, thank you to Paul and Joshua, the Atlas Copco representatives, for helping us get the compressors running.

Best regards,
Tyler

_______________________________________________
Dsg-rich mailing list
<a class="moz-txt-link-abbreviated" href="mailto:Dsg-rich@jlab.org">Dsg-rich@jlab.org</a>
<a class="moz-txt-link-freetext" href="https://mailman.jlab.org/mailman/listinfo/dsg-rich">https://mailman.jlab.org/mailman/listinfo/dsg-rich</a>
</pre>
        </blockquote>
        <pre wrap="">
</pre>
      </blockquote>
      <pre wrap="">
_______________________________________________
Dsg-rich mailing list
<a class="moz-txt-link-abbreviated" href="mailto:Dsg-rich@jlab.org">Dsg-rich@jlab.org</a>
<a class="moz-txt-link-freetext" href="https://mailman.jlab.org/mailman/listinfo/dsg-rich">https://mailman.jlab.org/mailman/listinfo/dsg-rich</a>
</pre>
    </blockquote>
    <br>
    <pre class="moz-signature" cols="72">-- 
George Jacobs
Jefferson Lab (TJNAF)
STE 12
12000 Jefferson Ave.
Newport News, VA 23606

(office) 757-269-7115

(cell)   757-876-0480

(email) <a class="moz-txt-link-abbreviated" href="mailto:jacobsg@jlab.org">jacobsg@jlab.org</a>

(website) <a class="moz-txt-link-freetext" href="https://userweb.jlab.org/~jacobsg">https://userweb.jlab.org/~jacobsg</a></pre>
  </body>
</html>