[Dsg-rtpc] RTPC Valve panel revision - added target and cathode purge gas supply - see attachment
Carlos Ayerbe
gayoso at jlab.org
Wed Aug 8 17:58:58 EDT 2018
Hi George,
thank you very much. Just to be sure that there is no confusion from my side.
- "To RTPC" is the line to the drift region, which we were always working. This line is 1/2", correct?
- "To Target and Cathode Volumes" are the lines to the regions we discussed today. It is one line in the scheme, but it is split in two afterwards, isn't it?. Also, they are 1/4", correct?
Thank you
-Carlos
----- Original Message -----
From: "George Jacobs" <jacobsg at jlab.org>
To: dsg-rtpc at jlab.org, "Carlos Ayerbe-Gayoso (gayoso at jlab.org)" <gayoso at jlab.org>
Sent: Wednesday, 8 August, 2018 17:07:32
Subject: RTPC Valve panel revision - added target and cathode purge gas supply - see attachment
Hi Carlos,
Please find attached pdf
I have added the gas supply for the purge of the target area and the cathode ( middle) volumes along with the bubblers for each.
I will have the P&I diagram revision completed in a couple days.
Cheers,
George
--
George Jacobs
Jefferson Lab (TJNAF)
STE 12
12000 Jefferson Ave.
Newport News, VA 23606
(office) 757-269-7021
(cell) 757-876-0480
(email) jacobsg at jlab.org (website) https://userweb.jlab.org/~jacobsg