[Dsg-rtpc] Moving on with the gas panel (test and more)
Carlos Ayerbe Gayoso
gayoso at jlab.org
Fri Feb 22 15:58:25 EST 2019
Hi all,
as many of you know, I finished the construction of the gas panel last Tuesday and the DSG team were so kind to visit W&M and make a visual inspection. As far I know, they are writing a small report of the visit and recommendations to move on.
>From W&M side, after some discussions with my advisor, I think I can summarize what we have in mind to move forward (edited from the internal communication):
1) install controllers and run the system using an inert gas (argon in our case)
2) Write the documentation on the design and components and specifications of the system. (replacement parts, fix broken parts, trouble-shoot, etc.)
3) An operations manual, suitable for a novice to turn on the system, regulate pressure and flow, and record data.
4) Incorporate Narbe's slow-controls when that becomes available.
In parallel, I will compile all the documentation related with the panel that could be requested by the DA.
Please be free to comment or provide suggestions to this plan.
Cheers
-Carlos
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-rtpc/attachments/20190222/96e18860/attachment.html>
More information about the Dsg-rtpc
mailing list