[dsg-svt] Nitrogen line monitoring/control
Yuri Gotra
gotra at jlab.org
Tue Jan 23 11:05:22 EST 2018
Yesterday a nitrogen cooling setup has been installed. In order to
optimize performance of the cooling the following modifications are
required. An MFC need to be installed on the line prior to the heat
exchanger. Nitrogen temperature monitoring need to be installed after
the heat exchanger prior to the split of the lines. These modifications
need to be propagated to the CSS interface. Thank you