[dsg-svt] DSG work request
Yuri Gotra
gotra at jlab.org
Fri Jul 13 09:55:49 EDT 2018
For testing the cooling system in preparation of the SVT for beam
operations it is critical to have measurements of the coolant flow. Both
flow meters observed issues with correct reading of the flow. The flow
meters have been disconnected from the cooling lines (control lines are
still connected). Please test the flow meters asap.
BAND detector will be installed in 2 weeks. There are several HFCB
temperature cables which run on top of the CVT cart. Please relocate
them to lower bins of the cart.
I did not receive a reply on the request about testing the spare modules
before and after kludging. Armen is working on kludging the modules and
DSG support in testing the modules is needed.
Thank you
-------------- next part --------------
A non-text attachment was scrubbed...
Name: gotra.vcf
Type: text/x-vcard
Size: 102 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-svt/attachments/20180713/b852cda6/attachment.vcf>
More information about the dsg-svt
mailing list