Dear All,
Armen started working on kludging the HV hybrid line on the SVT modules.
The plan is to put the HV jumpers on the spare modules first, then (when
MVT is re-integrated and tested), proceed with R4 modules. The work on
kludging and testing the SVT modules is expected to last for several
months depending on the available manpower and schedules for the DSG and
FE groups.
The work on kludging and testing the SVT modules will be performed in
the area of room EEL 124 where the work benches and SVT long term
stability test setup are located.
DSG help is needed in testing the modules before and after kludging.
Thank you
-------------- next part --------------
A non-text attachment was scrubbed...
Name: gotra.vcf
Type: text/x-vcard
Size: 102 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-svt/attachments/20180615/8f8aa4a2/attachment.vcf>
More information about the dsg-svt
mailing list