[dsg-hallb_svt] CLAS12 CVT integration status and near term schedule
Yuri Gotra
gotra at jlab.org
Fri May 14 16:24:06 EDT 2021
Dear Marco,
Here is the estimate and the updated schedule. Bob mounted the BMT on
the integration cart today, it is ready for the integration with the SVT.
For the external people critical for these tasks we would need support
from:
- *the survey group*. I put tentatively the surveys in the clean room on
5/18, before and after the CVT integration. The exact date will be
defined by Chris. The CVT alignment and survey in the hall will also
depend on this as it is the prerequisite for the transportation of the
CVT to the hall. The surveys in the clean room and in the hall would
take a day each based on the prior experience.
- *DSG*. We expect the main tasks related to cabling the CVT on the
space frame to be covered by them. Few days of work depending on the
allocated resources for this task.
- *Mohammad*. Per preliminary agreement he will help with the CVT
commissioning in the hall in June while I will be on vacation.
- *FE.* Ben (to install the SVT cosmic trigger, few hours). Mark (to
help with cable routing to the new cable tray that Bob is planning to
install for a clean safer path).
- *CEA team*. If CEA travel restrictions will be eased, CEA experts
would provide support installing the BMT services and commissioning the
DAQ. They would need an advance notice to plan the trip. Otherwise the
remote support will be needed. Few days of work depending on the
allocated resources for this task.
align and survey the SVT 5/18/21 5/18/21 PPE Survey
Mount the BMT on the integration cart 5/18/21 5/18/21 PPE Bob,Yuri,
Rafayel
align and survey the BMT 5/18/21 5/18/21 PPE Survey
Move CVT to the hall 5/24/21 5/24/21 Bob, Calvin, Morgan
Install CVT on the space frame 5/24/21 5/24/21 PPE Bob, Calvin, Morgan
align and survey the CVT 5/26/21 5/26/21 PPE Survey
Connect CVT services 5/27/21 6/7/21 PPE DSG, FE
Commission the CVT DAQ and services 6/7/21 6/21/21 Rafayel, Mohammad
install the SVT standalone trigger 6/21/21 6/21/21 FE (Ben)
Commission the CVT on cosmics, the SVT cosmic trigger, take alignment
sample 6/21/21 7/30/21 Yuri, Rafayel, Mohammad
On 5/12/21 8:13 PM, Marco Battaglieri wrote:
> Dear Yuri,
> another important milestone!
> Many thanks to you, Rafo, the Saclay team the JLab tech staff and the
> DSG that supported (and are supporting!!) this job.
> Please, let me have the list of (external) people critical for the
> next steps with the timeline of their presence on-campus: we are
> working on an extension of the access list and the is the right time
> to update it.
> Cheers
> marco
>
>> On 12 May 2021, at 12:27, Yuri Gotra <gotra at jlab.org
>> <mailto:gotra at jlab.org>> wrote:
>>
>> Dear All,
>>
>> BMT integration and cabling is complete. All tiles are operational,
>> tested with premix gas under the nominal HV settings. Pedestals are
>> posted to the HBMVT elog. BMT is being flushed with argon. Bob will
>> mount the BMT on the integration cart on Friday.
>>
>> SVT cabling is complete. All modules are operational, calibration
>> results are posted to the HBSVT elog. SVT sensors will be kept cold
>> until the survey.
>>
>> Per agreement with Chris next week the survey group will do SVT
>> survey and BMT alignment (after it is integrated with the SVT on the
>> cart).
>>
>> After the integration the CVT will be transported to the hall, craned
>> to the space frame, and mounted on the CVT cart. At this stage we
>> would need support from the Detector Support Group to rout and
>> connect the cables to the crates. We also rely on help from Mohammad
>> in June to commission the tracker and from the Fast Electronics group
>> on reinstalling the cosmic trigger to collect alignment data during
>> the summer time. If travel restrictions will be eased, CEA team will
>> join us on the work in the hall.
>>
>> Yuri and Rafayel
>>
>>
>>
>> <gotra.vcf>_______________________________________________
>> dsg-hallb_svt mailing list
>> dsg-hallb_svt at jlab.org <mailto:dsg-hallb_svt at jlab.org>
>> https://mailman.jlab.org/mailman/listinfo/dsg-hallb_svt
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20210514/a4167fdd/attachment.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: gotra.vcf
Type: text/x-vcard
Size: 102 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20210514/a4167fdd/attachment.vcf>
More information about the dsg-hallb_svt
mailing list