Krister Bruhwel is available to help with the CVT cabling.
Regards,
Bob
On 5/17/2021 11:11 AM, Brian Eng wrote:
> For the connecting services in the Hall it would be good if DSG could
> have someone from Hall B to help as well to sort of using this as a
> training session to help get them involved to expand on the list of
> people that can work on the SVT.
>
> ------------------------------------------------------------------------
> *From:* dsg-hallb_svt <dsg-hallb_svt-bounces at jlab.org> on behalf of
> Yuri Gotra <gotra at jlab.org>
> *Sent:* Friday, May 14, 2021 4:24 PM
> *To:* Marco Battaglieri <battagli at jlab.org>
> *Cc:* Eugene Pasyuk <pasyuk at jlab.org>; Sergey Boyarinov
> <boiarino at jlab.org>; Aune Stephan <stephan.aune at cea.fr>; Hattawy,
> Mohammad <mhattawy at odu.edu>; Marco Battaglieri
> <battaglieri at ge.infn.it>; Raffaella De Vita
> <Raffaella.Devita at ge.infn.it>; Benjamin Raydo <braydo at jlab.org>; Chris
> Gould <gould at jlab.org>; Christopher Curtis <curtis at jlab.org>; DEFURNE
> Maxime <maxime.defurne at cea.fr>; Chris Cuevas <cuevas at jlab.org>; Nathan
> Baltzell <baltzell at jlab.org>; Mark Taylor <taylorw at jlab.org>; Stepan
> Stepanyan <stepanya at jlab.org>; dsg-hallb_svt at jlab.org
> <dsg-hallb_svt at jlab.org>; Patrizia Rossi <rossi at jlab.org>; Bob Miller
> <rmiller at jlab.org>; Denny Insley <dinsley at jlab.org>; Rafayel
> Paremuzyan <rafopar at jlab.org>; Maxence Vandenbroucke
> <maxence.vandenbroucke at cea.fr>; Daniel Carman <carman at jlab.org>;
> MANDJAVIDZE Irakli <irakli.mandjavidze at cea.fr>
> *Subject:* Re: [dsg-hallb_svt] CLAS12 CVT integration status and near
> term schedule
>
> Dear Marco,
>
> Here is the estimate and the updated schedule. Bob mounted the BMT on
> the integration cart today, it is ready for the integration with the SVT.
>
> For the external people critical for these tasks we would need support
> from:
>
> - *the survey group*. I put tentatively the surveys in the clean room
> on 5/18, before and after the CVT integration. The exact date will be
> defined by Chris. The CVT alignment and survey in the hall will also
> depend on this as it is the prerequisite for the transportation of the
> CVT to the hall. The surveys in the clean room and in the hall would
> take a day each based on the prior experience.
>
> - *DSG*. We expect the main tasks related to cabling the CVT on the
> space frame to be covered by them. Few days of work depending on the
> allocated resources for this task.
>
> - *Mohammad*. Per preliminary agreement he will help with the CVT
> commissioning in the hall in June while I will be on vacation.
>
> - *FE.* Ben (to install the SVT cosmic trigger, few hours). Mark (to
> help with cable routing to the new cable tray that Bob is planning to
> install for a clean safer path).
>
> - *CEA team*. If CEA travel restrictions will be eased, CEA experts
> would provide support installing the BMT services and commissioning
> the DAQ. They would need an advance notice to plan the trip. Otherwise
> the remote support will be needed. Few days of work depending on the
> allocated resources for this task.
>
> align and survey the SVT 5/18/21 5/18/21 PPE Survey
> Mount the BMT on the integration cart 5/18/21 5/18/21 PPE
> Bob,Yuri, Rafayel
> align and survey the BMT 5/18/21 5/18/21 PPE Survey
> Move CVT to the hall 5/24/21 5/24/21 Bob, Calvin, Morgan
> Install CVT on the space frame 5/24/21 5/24/21 PPE Bob, Calvin,
> Morgan
> align and survey the CVT 5/26/21 5/26/21 PPE Survey
> Connect CVT services 5/27/21 6/7/21 PPE DSG, FE
> Commission the CVT DAQ and services 6/7/21 6/21/21 Rafayel, Mohammad
> install the SVT standalone trigger 6/21/21 6/21/21 FE (Ben)
> Commission the CVT on cosmics, the SVT cosmic trigger, take alignment
> sample 6/21/21 7/30/21 Yuri, Rafayel, Mohammad
>
> On 5/12/21 8:13 PM, Marco Battaglieri wrote:
>> Dear Yuri,
>> another important milestone!
>> Many thanks to you, Rafo, the Saclay team the JLab tech staff and the
>> DSG that supported (and are supporting!!) this job.
>> Please, let me have the list of (external) people critical for the
>> next steps with the timeline of their presence on-campus: we are
>> working on an extension of the access list and the is the right time
>> to update it.
>> Cheers
>> marco
>>
>>> On 12 May 2021, at 12:27, Yuri Gotra <gotra at jlab.org
>>> <mailto:gotra at jlab.org>> wrote:
>>>
>>> Dear All,
>>>
>>> BMT integration and cabling is complete. All tiles are operational,
>>> tested with premix gas under the nominal HV settings. Pedestals are
>>> posted to the HBMVT elog. BMT is being flushed with argon. Bob will
>>> mount the BMT on the integration cart on Friday.
>>>
>>> SVT cabling is complete. All modules are operational, calibration
>>> results are posted to the HBSVT elog. SVT sensors will be kept cold
>>> until the survey.
>>>
>>> Per agreement with Chris next week the survey group will do SVT
>>> survey and BMT alignment (after it is integrated with the SVT on the
>>> cart).
>>>
>>> After the integration the CVT will be transported to the hall,
>>> craned to the space frame, and mounted on the CVT cart. At this
>>> stage we would need support from the Detector Support Group to rout
>>> and connect the cables to the crates. We also rely on help from
>>> Mohammad in June to commission the tracker and from the Fast
>>> Electronics group on reinstalling the cosmic trigger to collect
>>> alignment data during the summer time. If travel restrictions will
>>> be eased, CEA team will join us on the work in the hall.
>>>
>>> Yuri and Rafayel
>>>
>>>
>>>
>>> <gotra.vcf>_______________________________________________
>>> dsg-hallb_svt mailing list
>>> dsg-hallb_svt at jlab.org <mailto:dsg-hallb_svt at jlab.org>
>>> https://mailman.jlab.org/mailman/listinfo/dsg-hallb_svt
>>> <https://mailman.jlab.org/mailman/listinfo/dsg-hallb_svt>
>>
--
Bob Miller
Hall B Lead Engineer
Jefferson Lab
757 822-9586
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_svt/attachments/20210517/aa3daed0/attachment-0001.html>
More information about the dsg-hallb_svt
mailing list