<p><font size="+1">Dear All,</font></p>
<p><font size="+1">BMT integration and cabling is complete. All
tiles are operational, tested with premix gas under the nominal
HV settings. Pedestals are posted to the HBMVT elog. BMT is
being flushed with argon. Bob will mount the BMT on the
integration cart on Friday.<br>
</font></p>
<p><font size="+1">SVT cabling is complete. All modules are
operational, calibration results are posted to the HBSVT elog.
SVT sensors will be kept cold until the survey.<br>
</font></p>
<p><font size="+1">Per agreement with Chris next week the survey
group will do SVT survey and BMT alignment (after it is
integrated with the SVT on the cart).</font></p>
<p><font size="+1">After the integration the CVT will be transported
to the hall, craned to the space frame, and mounted on the CVT
cart. At this stage we would need support from the Detector
Support Group to rout and connect the cables to the crates. We
also rely on help from Mohammad in June to commission the
tracker and from the Fast Electronics group on reinstalling the
cosmic trigger to collect alignment data during the summer time.
If travel restrictions will be eased, CEA team will join us on
the work in the hall.</font></p>
<p><font size="+1">Yuri and Rafayel<br>