[Dsg-hallc_controls] Fwd: back out HMS upgrade

Mike Fowler fowler at jlab.org
Thu Jul 19 15:24:32 EDT 2018


Communications working again.



On 7/19/2018 3:13 PM, Brian Eng wrote:
> Downgraded to 16 is complete.
>
> On Jul 19, 2018 14:04, Pablo Campero <campero at jlab.org> wrote:
>
>
>
>     ------------------------------------------------------------------------
>     *From: *"Steve Lassiter" <lassiter at jlab.org>
>     *To: *"Dsg-hallc_controls" <dsg-hallc_controls-bounces at jlab.org>
>     *Sent: *Thursday, July 19, 2018 1:39:51 PM
>     *Subject: *Re: back out HMS upgrade
>
>     Also there will be NO PSS lock up for Hall C this week.
>
>     Steven
>
>     ------------------------------------------------------------------------
>     *From: *"Steve Lassiter" <lassiter at jlab.org>
>     *To: *"Dsg-hallc_controls" <dsg-hallc_controls-bounces at jlab.org>
>     *Sent: *Thursday, July 19, 2018 1:35:01 PM
>     *Subject: *back out HMS upgrade
>
>     Hi guys,
>
>      Mike is telling me that the HMS is no longer talking via Ethernet.
>     The upgrade needs to be back out to Rslogix V16 asap!
>
>     Before taking the HMS controls off line, turn the valve keys to
>     manual. These are located on the front panel of the Controls racks
>     on the HMS carriage. Make sure to turn these back to PLC when
>     finished.
>
>     Steven
>
>
>
>
> _______________________________________________
> Dsg-hallc_controls mailing list
> Dsg-hallc_controls at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-hallc_controls


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallc_controls/attachments/20180719/6554ecce/attachment-0001.html>


More information about the Dsg-hallc_controls mailing list