Hi Xiangdong,
Tyler, Mary Ann, and I stopped by the lab to work on the NMR test for Rack #1. The computer will need to be connected to the network to perform some of the tasks that we need to do. Also, we were not able to turn on the power supply; were you able to plug it in yesterday? Please let us know when the rack is connected to the network and the power supply is plugged in, and we can proceed with our tests.
Regards,
Amanda