<html><body><div style="font-family: times new roman,new york,times,serif; font-size: 12pt; color: #000000"><div>Hi Amanda,<br></div><div><br data-mce-bogus="1"></div><div>I tried to test the NMR scan program this morning but the program hung up. Here is what I found before that point:<br data-mce-bogus="1"></div><div><br data-mce-bogus="1"></div><div>1. I could not use the program to set the current of IPS and ramp the field to where I want.<br data-mce-bogus="1"></div><div>2. The program hang up before the first cycle begins. (The run table tells to go to 0.0400T but the IPS displayed 0.0406T.)<br data-mce-bogus="1"></div><div><br data-mce-bogus="1"></div><div>Would you please take a look soon? I need to test and decide which NMR rack will be used by the end of this weekend. We are trying to start the HDice target cycle next week, the only time window to do it before September. Depends on the rack status, I may have to use the old NMR rack for now and resume testing the new rack next month, while the targets are being polarized. (If the I couldn't run the tests on the new NMR rack by tomorrow afternoon.)<br data-mce-bogus="1"></div><div><br data-mce-bogus="1"></div><div>Please take a look of the program asap.<br data-mce-bogus="1"></div><div><br data-mce-bogus="1"></div><div>Thanks,<br data-mce-bogus="1"></div><div><br data-mce-bogus="1"></div><div>Xiangdong<br data-mce-bogus="1"></div><div><br></div><div data-marker="__SIG_PRE__"><p><em><span style="FONT-FAMILY: courier new,courier,monaco,monospace,sans-serif"><strong>Xiangdong Wei</strong></span></em></p>
<p><em><span style="FONT-FAMILY: courier new,courier,monaco,monospace,sans-serif"></span></em><span style="FONT-FAMILY: courier new,courier,monaco,monospace,sans-serif"><span data-mce-style="font-size: small;" style="font-size: small;">x-5266</span></span></p></div><br><hr id="zwchr" data-marker="__DIVIDER__"><div data-marker="__HEADERS__"><b>From: </b>"Amanda Hoebel" <amandah@jlab.org><br><b>To: </b>dsg-hdice@jlab.org<br><b>Cc: </b>"Patrizia Rossi" <rossi@jlab.org><br><b>Sent: </b>Thursday, July 13, 2017 10:41:03 AM<br><b>Subject: </b>[dsg-hdice] Synchronization date evaluation<br></div><br><div data-marker="__QUOTED_TEXT__">Hello,<br><br>Dr. Sandorfi stopped by the DSG control room 7/11/17 to inquire about the status of the CT-box with synchronization. He would like the synchronization by the end of September. We are evaluating the feasibility of this deadline because we are working on many other projects for the upcoming fall run.<br><br>We are also waiting on program testing for NMR, FRS, and RTP.<br><br>Regards,<br>Amanda<br>_______________________________________________<br>dsg-hdice mailing list<br>dsg-hdice@jlab.org<br>https://mailman.jlab.org/mailman/listinfo/dsg-hdice<br></div></div></body></html>