[Eesic] Machine Down South Side due to Cryo Problem
Peter Anthony Francis
francis at jlab.org
Mon Feb 13 06:44:39 EST 2017
Well,
I guess we got lucky, Ops just got the Machine back to Beam Permit
around the entire machine.
No Maintenance day today.
On 2/13/2017 5:30 AM, Peter Anthony Francis wrote:
> Good Morning Everyone,
>
> I think Ops might start Tuesdays maintenance day today due to South
> Linac Cryo Problems.
>
> North Linac is in Power Permit and South Side is in Controlled.
>
> Make Sure you have Atlis and call Ops before any work.
>
>
>