[Eg6_analysis] pass2 status

Nathan Baltzell baltzell at jlab.org
Wed Sep 17 08:58:35 EDT 2014


Hi Lamiaa, EG6,

I planned to do that data last.  I assumed no one is immediately interested
in it;  it is TPC commissioning data before fixing voltages/daq settings, and
we’ve not seen any analysis of  those He-4 runs in the past 3 years.  Let me
know if anyone disagrees!

-Nathan



On Sep 16, 2014, at 22:22, Lamiaa El Fassi <lamiomar at gmail.com> wrote:

> Hi Nathan, Hi All,
> 
> I have updated the CSQL monitoring web-page with the entries of the ongoing pass2 1.2 GeV cooking; this link.
> I noticed that the early processed 1.2 GeV runs started from the actual production run # 61448. I am not sure what is the decision in this pass 
> concerning the runs taken before that (starting from 61218), are you willing to process them later or did you decide, for example, to drop them? 
> Please apologize my curiosity :).
> 
> Currently I am making all the CSQL monitoring plots with the entries of ONLY one file of each run. However, if you want to see all run-files entries 
> on these plots I will happy to update them at least for this pass. The plots may become more crowded compared to now, but it will reflect the behavior 
> of the whole data-sets file-by-file! Please let me know what do you think concerning this point.
> 
> 
> Best regards,
> 
> Lamiaa
> 
> *********************************************************************
> * Assistant Prof. Lamiaa El Fassi     email: elfassi at jlab.org
> *********************************************************************    
> * Phone: (662) 325-2806                 
> * 125 Hilbun Hall
> * Lee Blvd, Box 5167
> * Mississippi State, MS 39762  
> *********************************************************************
> 
> On Mon, Sep 15, 2014 at 9:17 AM, Nathan Baltzell <baltzell at jlab.org> wrote:
> FYI All,
> 
> Early 1.206 GeV data is complete, and late 1.269 GeV is in progress.
> Full HROOT is going to disk (I turned off skims for 1 GeV, since 1-electron
> doesn’t do much, and 3-gammas is probably pointless):
> 
> /volatile/clas/claseg6/pass2/1p2gev/HROOT
> 
> As discussed in last week’s meeting, next will be 5.7, and then 6, to try
> to have some complete data sets before next Wednesday’s maintenance.
> 
> -Nathan
> _______________________________________________
> Eg6_analysis mailing list
> Eg6_analysis at jlab.org
> https://mailman.jlab.org/mailman/listinfo/eg6_analysis
> 
> _______________________________________________
> Eg6_analysis mailing list
> Eg6_analysis at jlab.org
> https://mailman.jlab.org/mailman/listinfo/eg6_analysis




More information about the Eg6_analysis mailing list