[Eicatjlab_all_personnel] [EXTERNAL] EIC Monthly EVMS Results (CPRs) for April 2025

Rassner, Donna drassner at bnl.gov
Fri May 9 16:47:48 EDT 2025


Sent on behalf of Gerald Layden


EIC Team,

April 2025 earned value reporting against the CD-3A baseline and the AD internal baseline is complete. The Contractor Performance Reports (CPR) have been posted on the CAM EVMS site:[https://res-h3.public.cdn.office.net/assets/mail/file-icon/png/folder_16x16.png]CPRs (Contractor Performance Reports)<https://urldefense.proofpoint.com/v2/url?u=https-3A__brookhavenlab.sharepoint.com_sites_eRHIC_evms_ReadOnly-2520Area_Forms_AllItems.aspx-3Fid-3D-252Fsites-252FeRHIC-252Fevms-252FReadOnly-2520Area-252FCPRs-2520-2528Contractor-2520Performance-2520Reports-2529-26viewid-3Db480953f-252D523f-252D4b93-252D8f34-252D67b82f5565c1&d=DwIFAg&c=CJqEzB1piLOyyvZjb8YUQw&r=d0KG5O9luo0FhuYP-_C2VbpBNln9iudksZOBnX13nypLFx5Y3VKB85tQJ8VLc-jR&m=79Mcle5GYENFtgxVwHZfnUYhViTxRlIPnhVkFVKzKDjJVq9ub0cOjw3_A3L6IqOU&s=6ohpUaGHJsNrcBDt5-nc1Nvgc1hq5uJqYdMCV0qtpbM&e= >

Results:

  *   CD-3A scope - Four control account(s) & two L2s tripped current period and/or cumulative variance thresholds requiring a VAR explanation

  *   Associated Design (AD) - Three control account(s) & one L2s tripped current period and/or cumulative variance thresholds requiring a VAR explanation

Variance Analysis Reports (VARs), through approval, are due Tuesday, May 13th.

Please review the CPRs and reach out to your PC analyst with any questions.
Respectfully,
Gerald Layden | EIC Project | Project Mgmt Analyst | glayden at bnl.gov<mailto:glayden at bnl.gov> | Mobile: 843-696-7674




-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/eicatjlab_all_personnel/attachments/20250509/bef8ff16/attachment-0001.htm>


More information about the Eicatjlab_all_personnel mailing list