[Esr-users] Cooldown of Hall C target

Joe D. Wilson, Jr jwilson at jlab.org
Wed Jan 24 08:27:27 EST 2018


Hello,

As of 0800 on 23Jan18 (today), it was announced at MCC that the Hall C 15K target cooldown may occur on late afternoon today, pending information update. Of course, the Cryogenics Department appreciates any updates with respect to any anticipated changes to the ESR loads.

Thanks!

 

-----------------

Joe D. Wilson, Jr.

Cryogenic Operations Engineer

 

Jefferson Lab

 <http://www.jlab.org/> www.jlab.org

757-269-7722

 <mailto:jwilson at jlab.org> jwilson at jlab.org

 

 

From: Joe D. Wilson, Jr [mailto:jwilson at jlab.org] 
Sent: Tuesday, January 23, 2018 6:45 PM
To: 'esr-users at jlab.org' <esr-users at jlab.org>
Subject: FW: Cool down of Hall C target

 

From: David Meekins [mailto:meekins at jlab.org] 
Sent: Tuesday, January 23, 2018 6:40 PM
To: Christopher Perry <cperry at jlab.org <mailto:cperry at jlab.org> >; Joe Wilson <jwilson at jlab.org <mailto:jwilson at jlab.org> >
Cc: Christopher Keith <ckeith at jlab.org <mailto:ckeith at jlab.org> >; Dave Kashy <kashy at jlab.org <mailto:kashy at jlab.org> >; Heidi Fansler <fansler at jlab.org <mailto:fansler at jlab.org> >
Subject: Cool down of Hall C target

 

Hi Chris and Joe,

 

I discovered that my phone is no longer sending mails so I apologize for not sending notice to you that Hall C would like to cool down their target in the AM on 1/24. We anticipate that this will take about 4 hours to get onto the cold return and another 4 hours to condense the H2/D2.

 

Thanks

 

David Meekins
Staff Scientist
Thomas Jefferson National Accelerator Facility
12000 Jefferson Ave
Newport News Va.  23606

Office:  757-269-5434
Cell:  757-968-9076

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/esr-users/attachments/20180124/5af7b2d3/attachment.html>


More information about the Esr-users mailing list