[Esr-users] Cryogenic operation and recovery priority for Halls A, B, C

David Kashy kashy at jlab.org
Tue Oct 29 11:09:17 EDT 2019


Probir,
This is fine. If new hardware is being tested or loads being added, then a post to esr-users at jlab.org should be made in addition to contacting Chris Perry prior to starting and again after finishing any test. If an abnormal event occurs please write to the same list and make a log entry in the CLOG and explain what happened and when.

Thanks
Dave

________________________________
From: Probir Ghoshal <ghoshal at jlab.org>
Sent: Tuesday, October 29, 2019 10:55 AM
To: David Kashy <kashy at jlab.org>
Cc: esr-users at jlab.org <esr-users at jlab.org>; Rolf Ent <ent at jlab.org>; Ruben Fair <rfair at jlab.org>
Subject: Re: [Esr-users] Cryogenic operation and recovery priority for Halls A, B, C

Dave
You may be aware that both supercon magnets in hall b is scheduled to run to full field by end of this week and we are planning to charge both magnets either tomorrow or Thursday...!
Please let us know if that is okay

Regards,
Probir

On Oct 29, 2019, at 10:44 AM, David Kashy <kashy at jlab.org<mailto:kashy at jlab.org>> wrote:

Hi All,
As determined by Rolf and Javier, the priority to recover or keep the the systems cold is the following.
Hall C has first priority
Hall A is second
Hall B is last

If this changes an update will be announced.
If you have questions, please let me know.

Thanks
Dave

_______________________________________________
Esr-users mailing list
Esr-users at jlab.org<mailto:Esr-users at jlab.org>
https://mailman.jlab.org/mailman/listinfo/esr-users
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/esr-users/attachments/20191029/5615e9cc/attachment.html>


More information about the Esr-users mailing list