[Esr-users] [New Logentry] Follow-up Re: Buffer Dewar 4 K supply and Return U-tube removal

mcookiv at jlab.org mcookiv at jlab.org
Thu Dec 12 10:45:02 EST 2024


Logentry Text:
--
The work was stopped. During the pre-job briefing it was realized that all of the valves (4K supply, 4K return, warm return) are closed and there isn't any pressure in the buffer dewar.  As we are unsure when the valves were closed and the level of contamination the dewar may have, the current procedure is no longer applicable and will be re-written. We will re-start the first week of January 2025

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4323493
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/esr-users/attachments/20241212/a4cd92b7/attachment-0001.html>