[Esr-users] [New Logentry] Follow-up Re: Follow-up Re: Follow-up	Re: Hall B dewar disconnect and 4K circuit purification check	and cleanup
    kashy at jlab.org 
    kashy at jlab.org
       
    Sat Jan 11 12:15:02 EST 2025
    
    
  
Logentry Text:
--
At 06:20 this morning I increased the flow rate of warmu flow to 0.75g/s by allowing the pressure at PT8512 go to 3 atm. The 4K circuit in the DBX is all above 285K. Hopefully by Monday moring the entire circuti will be warm. We will need to determine if we do investigation of PV8512S. So far no significatn contamination has been observed.
---
This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4325859