We plan to conduct the power-up test of MOLLER TM3 magnet from late afternoon (3:30 PM) 9/24/2025 to 10/8/2025. We could end the test earlier than 10/8. The testing will be on and off. We will test the magnet up to 4000 A. The maximum power consumption of the magnet is 138 kW. The required flow rate of LCW is 23 gallons per minute.