[Evpo] 12 GeV - North and South LINAC Power Upgrades, September Accruals

Kent Stephenson tks at jlab.org
Mon Oct 4 09:38:00 EDT 2010


Attached is the September accrual report for the 12 GeV - North and 
South LINAC Power Upgrades project.  This is my first accrual report and 
I believe it is on the correct form.  The estimated amount for the 
September invoice is $95,639.00 (18.5%) based on the work completed in 
September and Schedule of Values (Prices).  This results in a total to 
date of $515,674.00 (99.75%).  Also, CCRs 1 and 2 were completed in 
September.  The total for these is $24,897.78 or 95.76% of the contract 
contingency funds.  The total invoiced amount for the work performed for 
CCR2 will be $5,924.28 of which 60% ($3,554.57) is funded by electrical 
infrastructure funds (Paul Powers).  The contractor indicates that he 
does not plan to include the CCRs in the September invoice.

Kent Stephenson
ext. 6162

-------------- next part --------------
A non-text attachment was scrubbed...
Name: N&S Linac pwr upgrade September accrual.xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 26513 bytes
Desc: not available
Url : https://mailman.jlab.org/pipermail/evpo/attachments/20101004/ca29b9a4/attachment-0001.bin 


More information about the Evpo mailing list