[Evpo] Subcontract PO Accruals - July 2018
Robert Norton
norton at jlab.org
Tue Jul 31 16:08:57 EDT 2018
Attached is the invoice form for PO373774 (CHL 2K SC1R cold box cold
compressors).
I believe this was approved for payment and so the below listed
exception in bold/underlined is applicable.
On 7/31/2018 8:17 AM, Matthew Krug wrote:
> All,
>
> If you are receiving this message it means you are responsible for
> submitting accrual estimates for at least one Subcontract Purchase Order.
>
> This is a reminder to complete a Subcontract Percent Complete Form for
> any cost for work completed through July 31, 2018. It is important
> that we receive estimated percent complete forms associated with work
> performed through July 31, 2018 in which an invoice has not been
> received or approved for payment .
>
> ***** Please submit your accrual form by Friday, August 3, 2018. If
> needed, I have attached the instructions and form. *****
>
> *If you determine that there is nothing to accrue please e-Mail
> EVPO at jlab.org and provide the PO #*. Otherwise, please complete and
> forward the PO Percent Complete form and*email to: EVPO at jlab.org .*
>
>
> Thanks for your help.
>
> Matthew Krug (Matt)
> Financial Systems Manager
> Jefferson Lab
> 757.269.7120
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/evpo/attachments/20180731/3aa88f38/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: USALNAMINV685539050629182003-2.PDF
Type: application/pdf
Size: 108266 bytes
Desc: not available
URL: <https://mailman.jlab.org/pipermail/evpo/attachments/20180731/3aa88f38/attachment-0001.pdf>
More information about the Evpo
mailing list