Hi Connie,
The following subcontracts that I administer are status as per below.

15-C1196 LCLS-II 4.5K CB – no accrual this month
16-C0737 LCLS-II 2k CC  – no accrual this month
18-C0415 SC1R 2K CC – no accrual this month
20-C0007 SNS PPU Vacuum Vessels – no accrual this month
20-C0009 SNS PPU Tuner Frames – no accrual this month – all remaining lines will come in in June.
20-C0011 JLab EBW Upgrade – no accrual this month

Please let me know if you or anyone else have any questions.
Thanks,
Ted

Ted Peshehonoff, JLab Subcontracting Officer, 757-269-5139

From: Connie Adams <cadams at jlab.org>
Sent: Monday, June 1, 2020 4:22 PM
To: Matthew Krug <mkrug at jlab.org>; Melissa Torres <torres at jlab.org>; Connor Kaufmann <connork at jlab.org>; Ted Peshehonoff <tvp at jlab.org>; Dana Arenius <arenius at jlab.org>; Mike Bevins <mbevins at jlab.org>; Christopher Scanlon <scanlon at jlab.org>; Robert Norton <norton at jlab.org>; Jason Willoughby <jasonw at jlab.org>; Giuseppina Tenbusch <jessie at jlab.org>; Tanya Gaye Stewart <fraites at jlab.org>; Michele Khasidis <michele at jlab.org>; Denise Leary-Stith <greene at jlab.org>; Thomas Huratiak <huratiak at jlab.org>; James Coleman <colemanj at jlab.org>; Steven Lassiter <lassiter at jlab.org>; Carolyn Stepney <stepney at jlab.org>; Jason Willoughby <jasonw at jlab.org>; Thomas Renzo <renzo at jlab.org>; Katherine Wilson <kwilson at jlab.org>; Naeem Huque <huque at jlab.org>; Gary Cheng <cheng at jlab.org>; Russell Fries <rfries at jlab.org>; Mitchell Laney <laney at jlab.org>; Rusty Sprouse <sprouse at jlab.org>; Eden Evans <eaevans at jlab.org>; Kelly Krug <krug at jlab.org>; Phillip Kessler <pkessler at jlab.org>; Jenita Everett <jeverett at jlab.org>; Joe Dougherty <cecild at jlab.org>; Linda Stinnett <stinnett at jlab.org>; Connie Adams <cadams at jlab.org>
Subject: Subcontract PO Accruals

All,

If you are receiving this message it means you are responsible for submitting accrual estimates for at least one Subcontract Purchase Order.

This is a reminder to complete a Subcontract Percent Complete Form for any cost for work completed through May 31, 2020. It is important that we receive estimated percent complete forms associated with work performed through May 31, 2020 in which an invoice has not been received or approved for payment .

**** Please submit your accrual form by Wednesday, June 3, 2020. If needed, I have attached the instructions and form. ****

If you determine that there is nothing to accrue please e-Mail EVPO at jlab.org<mailto:EVPO at jlab.org> and provide the PO #. Otherwise, please complete and forward the PO Percent Complete form and email to: EVPO at jlab.org<mailto:EVPO at jlab.org>.


Thanks for your help!!!

Connie Adams
Financial Systems Accountant
JSA/Jefferson Lab
757-269-5108
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/evpo/attachments/20200601/b2f08fed/attachment.html>


More information about the Evpo mailing list