[Evpo] Subcontract PO Accruals - 2nd Request

Thomas Huratiak huratiak at jlab.org
Mon Apr 5 07:41:45 EDT 2021


I know Chris was out late last week and I'm not sure if he'll be back before the accrual deadline or not.

For PO # 21-C0007 - No accrual for the month of March.  Supplier is still waiting to receive one last item before PO line # 2 is complete.

Tom


From: Connie Adams <cadams at jlab.org>
Sent: Friday, April 2, 2021 8:06 PM
To: Tom Renzo <renzo at jlab.org>; Todd Kujawa <kujawa at jlab.org>; Sarin Philip <philip at jlab.org>; Chris Perry <cperry at jlab.org>
Cc: Russ Fries <rfries at jlab.org>; Thomas Huratiak <huratiak at jlab.org>; Matthew Krug <mkrug at jlab.org>; Connie Adams <cadams at jlab.org>
Subject: Subcontract PO Accruals - 2nd Request

All,

You received the below request because you are the primary (To:) or alternate (cc:) person responsible for submitting accrual estimates for at least one Subcontract Retainage (Accrual) Purchase Order.

Submittals were requested by COB today.  It is imperative that we receive a response by noon Monday, 4/05/2021.

Please complete the Subcontract Percent Complete Form (PO Accrual Form) for work completed through March 31, 2021. It is important that we receive estimated percent complete forms associated with work performed through this date for which we have a contractual obligation where an invoice has not been received and approved.

Please submit your accrual form to evpo at jlab.org<mailto:evpo at jlab.org>.  If you have nothing to accrue, please email the address provided stating you have nothing to accrue for PO# xxx-xxxxxx.

Thanks!

Connie Adams
Financial Systems Accountant
JSA/Jefferson Lab
757-269-5108


From: Connie Adams
Sent: Wednesday, March 31, 2021 5:05 PM
To: Christopher Keith <ckeith at jlab.org<mailto:ckeith at jlab.org>>; Chris Perry <cperry at JLAB.ORG<mailto:cperry at JLAB.ORG>>; Tanya Gaye Stewart <fraites at jlab.org<mailto:fraites at jlab.org>>; Naeem Huque <huque at JLAB.ORG<mailto:huque at JLAB.ORG>>; Thomas Huratiak <huratiak at jlab.org<mailto:huratiak at jlab.org>>; Todd Kujawa <kujawa at jlab.org<mailto:kujawa at jlab.org>>; Katherine Wilson <kwilson at jlab.org<mailto:kwilson at jlab.org>>; Steven Lassiter <lassiter at jlab.org<mailto:lassiter at jlab.org>>; Matt Marchlik <marchlik at jlab.org<mailto:marchlik at jlab.org>>; Rick Nelson <nelson at jlab.org<mailto:nelson at jlab.org>>; Sarin Philip <philip at jlab.org<mailto:philip at jlab.org>>; Peter Owen <powen at jlab.org<mailto:powen at jlab.org>>; Tom Renzo <renzo at JLAB.ORG<mailto:renzo at JLAB.ORG>>; Russ Fries <rfries at jlab.org<mailto:rfries at jlab.org>>; John Riesbeck <riesbeck at jlab.org<mailto:riesbeck at jlab.org>>; Christine Snetter <snetter at jlab.org<mailto:snetter at jlab.org>>; Melissa Torres <torres at jlab.org<mailto:torres at jlab.org>>; Ted Peshehonoff <tvp at JLAB.ORG<mailto:tvp at JLAB.ORG>>; Celia Whitlatch <whitlatc at jlab.org<mailto:whitlatc at jlab.org>>
Cc: Joel Dolbeck <dolbeck at jlab.org<mailto:dolbeck at jlab.org>>; Gianluigi Ciovati <gciovati at jlab.org<mailto:gciovati at jlab.org>>; Jason Willoughby <jasonw at jlab.org<mailto:jasonw at jlab.org>>; Giuseppina Tenbusch <jessie at JLAB.ORG<mailto:jessie at JLAB.ORG>>; Stephen Wood <saw at jlab.org<mailto:saw at jlab.org>>; Alexander Somov <somov at jlab.org<mailto:somov at jlab.org>>; Sharon Parkinson <spark at jlab.org<mailto:spark at jlab.org>>; Matthew Krug <mkrug at JLAB.ORG<mailto:mkrug at JLAB.ORG>>; Connie Adams <cadams at jlab.org<mailto:cadams at jlab.org>>
Subject: Subcontract PO Accruals

All,

You are receiving this message because you are the primary (To:) or alternate (cc:) person responsible for submitting accrual estimates for at least one Subcontract Retainage (Accrual) Purchase Order. Attached you will find the listing of Subcontract Retainage (Accrual) Purchase Orders that need to be evaluated for accrual purposes. Additionally, you will find the PO Accrual Form with instructions to be completed for your submittal.

Please complete the Subcontract Percent Complete Form for work completed through March 31, 2021. It is important that we receive estimated percent complete forms associated with work performed through this date for which we have a contractual obligation where an invoice has not been received and approved.

**** Please submit your accrual form to evpo at jlab.org<mailto:evpo at jlab.org> by close of business, Friday, April 2, 2021. If you have nothing to accrue, please email the address provided stating you have nothing to accrue for PO# xxx-xxxxxx. ****

Thanks for your help!!!

Connie Adams
Financial Systems Accountant
JSA/Jefferson Lab
757-269-5108

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/evpo/attachments/20210405/0ddf3a9c/attachment.html>


More information about the Evpo mailing list