[Utility Outage] Completed Power Outage - 07/29/2013 08:00

J. Willoughby jasonw at jlab.org
Mon Aug 5 13:44:39 EDT 2013


The following Power Outage has been Completed:

Outage:      Test Lab P4 Outage
Proposed By: J. Willoughby
Start Time:  07/29/2013 08:00
End Time:    07/29/2013 09:00
Description: Remove power from P4 in the Test Lab to disconnect temporary construction power.  This will remove power from T-22 which feeds 1700 in the Test Lab.  1700 feeds the cryo racks near the CMTF control room.

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=1