[Utility Outage] Scheduled HVAC Outage - 08/07/2013 10:50
Carroll W. Jones
jonesc at jlab.org
Wed Aug 7 13:34:17 EDT 2013
The following HVAC Outage has been Confirmed:
Outage: Startup CUP Building Chiller for Seal Leak Troubleshooting
Proposed By: Carroll W. Jones
Start Time: 08/07/2013 10:50
End Time: 08/07/2013 11:30
Description: CUP chiller is being started to troubleshoot seal leak. No leak is apparent with chiller off. The chilled water loop will be separated into two sections. TLA, Test Lab highbay, and F-Wing will be on CUP chiller loop. The Test Lab north addition, EEL, and Accelerator Chilled Water heat exchanger will be on Test Lab basement chiller loop. No significant temperature change should occur but the F-Wing will notice the transition.
For additional information or clarification, please contact Carroll W. Jones at 757-876-1778.
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=7