[Utility Outage] Scheduled Control System Outage - 07/17/2013 06:00
Carroll W. Jones
jonesc at jlab.org
Tue Jul 16 22:58:02 EDT 2013
The following Control System Outage has been Confirmed:
Outage: Test Lab Cooling Tower and CUP Chiller and Pumps Switching to Manual Operation
Proposed By: Carroll W. Jones
Start Time: 07/17/2013 06:00
End Time: 07/17/2013 12:00
Description: The Test Lab Cooling Tower fans, the Test Lab Cooling Tower pumps, the CUP Building 800 ton chiller, and the CUP Building chilled water pumps (primary and secondary) will be switched from automatic operation to manual operation Wednesday morning at approximately 0600 to maintain chiller plant operations during an electrical outage affecting control electrical power. Equipment will be switched back to automatic operation after the electrical work is complete. No modifications to controls will occur. Systems supported by Test Lab cooling tower heat rejection and chiller plant heat rejection should not be adversely impacted during this work.
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=3