[Utility Outage] Proposed HVAC Outage - 06/13/2013 15:00

Carroll W. Jones meier at jlab.org
Wed Jun 12 10:01:16 EDT 2013


The following HVAC Outage has been Proposed:

Outage:      Troubleshoot Test Lab TLA Phoenix System Communication & Exhaust Airflow Mod
Proposed By: Carroll W. Jones
Start Time:  06/13/2013 15:00
End Time:    06/13/2013 17:00
Description: Troubleshoot Phoenix Valve Control System communication and lower Production Chem Room and R&D Chem Room new fume hood exhaust flow values from 1200 CFM to 780 CFM.  Production Chem Room values would be changed first and then R&D Chem Room values.  Older fume hood and Horizontal EP Tool exhaust flow values will not be changed.  No airflow changes will be made to T-Trench tools.