The following HVAC Outage has been Proposed:
Outage: Replace American Automatrix Sage Controller with Two Honeywell JACE Controllers
Proposed By: Carroll W. Jones
Start Time: 06/17/2013 00:27
End Time: 06/17/2013 00:27
Description: Accelerator Chilled Water Loop pump VFD will be closely monitored during execution of switchover from Sage to JACE controllers. If operational Accelerator Chilled Water Loop pump VFD stops providing adequate pressure to the chilled water loop, the pump shall be switched to bypass mode and valves manually modulated to provide the desired abouve of chiiled water to Accelerator site Service Buildings.