[Utility Outage] Scheduled Road Closure - 06/28/2013 08:00
Celia Whitlatch
whitlatc at jlab.org
Tue Jun 25 13:55:00 EDT 2013
The following Road Closure has been Confirmed:
Outage: North and South Linac AC Project
Proposed By: Celia Whitlatch
Start Time: 06/28/2013 08:00
End Time: 06/28/2013 11:00
Description: Bohr Road North and South will be closed temporarily (about an 1hr) on Friday while the new air handling units on unloaded by a crane.
The North road will be closed first beginning at 8am. After unloading the AHU the crane will move to the south and the South road will then be closed.
For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=15