[Utility Outage] Scheduled Power Outage - 10/14/2013 08:00

J. Willoughby jasonw at jlab.org
Mon Oct 14 08:48:01 EDT 2013


The following Power Outage has been Confirmed:

Outage:      TVSS repair
Proposed By: J. Willoughby
Start Time:  10/14/2013 08:00
End Time:    10/15/2013 17:00
Description: 30 minute outages per unit that needs to be replaced.

Building 58


EAP-MC-1
DP-LAB-1
AP-LAB-6
AP-LAB-8
AP-LAB-7
AP-LAB-17
DP-LAB-9
AP-LAB-15

Building 55
LP-1-1
AP-1-1
AP-1-4
AP-1-5
AP-1-3A
AP-1-3B
AP-1-7B

Building 60

TL101