[Utility Outage] Scheduled Power Outage - 10/17/2013 06:00

J. Willoughby jasonw at jlab.org
Tue Oct 15 07:06:55 EDT 2013


The following Power Outage has been Confirmed:

Outage:      LP-2-1, ELP-LS-1-1
Proposed By: J. Willoughby
Start Time:  10/17/2013 06:00
End Time:    10/17/2013 12:00
Description: Remove power from LP-2-1 to replace MCB.  LP-2-1 will remove main lighting from the entire second floor.  Emergency lighting will still be operational.

For more details, visit the webpage listed below:
https://cc.jlab.org/cgi-bin/infrastructure/Outage/OutageView?ident=5