The following Power Outage has been Completed:
Outage:      Counting House Emergency Power - First Floor
Proposed By: Paul Powers
Start Time:  07/10/2014 06:00
End Time:    07/10/2014 08:00
Description/Impacts:
Power Outage of panel CHEMP2 in the first floor of the Counting House to tie in 4 circuits for Counting Room A.  This will interrupt all circuits in this panel.  This will affect all counting rooms and the PSS system.
Impacted Areas:
	Bldg 97: Counting House